Delay in getting export MPAN

  • February 1, 2023
  • 20 replies
  • 1585 views

I am not an Ovo customer . My FIT paid by Scottish Power.  application made for export guarantee payments made over 8 months ago and I’m now advised that “Ofgem delays” mean another 2/3 months wait. I applied as soon as my smart meter was fitted ( Mar 2022).

any similar experiences? and how to put pressure on?  I was under the impression that all solar pv  producers were encouraged to help national supply.

Whats the issue with Ofgem ( if any?)

Best answer by BPLightlog

Not sure why Ofgem would be involved in this at all.

Unless you have two separate solar strings you will only have either FIT (feed in Tariff) or SEG (Smart Export Guarantee) not both. As long as you have your system details, MCS certification (or equivalent) etc it is a matter of registration and acceptance as far as I am aware. 

20 replies

BPLightlog
Super User
Super User
February 1, 2023

Not sure why Ofgem would be involved in this at all.

Unless you have two separate solar strings you will only have either FIT (feed in Tariff) or SEG (Smart Export Guarantee) not both. As long as you have your system details, MCS certification (or equivalent) etc it is a matter of registration and acceptance as far as I am aware. 

Bring me Sunshine ~ E&E {Solar PV, Battery Storage, Hybrid EV, ASHP and Home Assistant automation}
jaybellAuthor
Rank 5
February 8, 2023

I have now been advised that my Export MPAN has been created but not yet registered with my FIT buyer.  How and to whom do I complain about the excessive delays?

Blastoise186
Super User
Super User
February 8, 2023

https://ovoenergy.com/feedback if that happens to be OVO.

Otherwise, whoever the FiT/SEG Supplier is

Securing energy by zapping security bugs... For that is The Blastoise Way! Remember, I'm just like you - AI Powered Evil Geniuses aren't Staff!
Jeffus
Rank 20
Rank 20
February 8, 2023

I have now been advised that my Export MPAN has been created but not yet registered with my FIT buyer.  How and to whom do I complain about the excessive delays?

You say you are with Scottish Power for FIT, so

https://www.scottishpower.co.uk/support-centre/complaints

jaybellAuthor
Rank 5
February 15, 2023

I enquired of British Gas how long it would take to get registered for Export,  they replied as follows

Thanks for your interest in becoming a British Gas Smart Export Guarantee customer. Unfortunately, we're unable to accept your application because you’re already receiving export payments under the Feed in Tariff (FiT) scheme.

Im sure this is incorrect

comments?
 

Blastoise186
Super User
Super User
February 15, 2023

If you are already receiving FiT, you can’t get SEG as well. It sounds like you applied for the wrong scheme.

Securing energy by zapping security bugs... For that is The Blastoise Way! Remember, I'm just like you - AI Powered Evil Geniuses aren't Staff!
BPLightlog
Super User
Super User
February 15, 2023

@jaybell if you registered for FIT you don’t need to register again for SEG. I may be wrong but it sounds as if you have had a solar system for a while (FIT applications were ended some time ago but existing systems remain on it).

If you have had a smart meter fitted as you mention, you don’t need to re-register and being on the FIT scheme is better financially than SEG. 
Hope that makes sense. 

Bring me Sunshine ~ E&E {Solar PV, Battery Storage, Hybrid EV, ASHP and Home Assistant automation}
jaybellAuthor
Rank 5
February 16, 2023

BPlightlog..thanks.  I am keeping my FIt and only wish to change my “deemed” export to a buyer under the SEG guarantee.  This is allowed. So I am looking for electricity buyers to take my export, and the British gas enquiry produced the result I quoted above.

if I can export under SEG it will benefit me as I am producing power from panels that are well in excess of my usage and I want to benefit from that with a better rate than the deemed export rate which assumes only 50%.

However if I install storage batteries cab I still get SEG export?

 

 

Jeffus
Rank 20
Rank 20
February 16, 2023

BPlightlog..thanks.  I am keeping my FIt and only wish to change my “deemed” export to a buyer under the SEG guarantee.  This is allowed. So I am looking for electricity buyers to take my export, and the British gas enquiry produced the result I quoted above.

if I can export under SEG it will benefit me as I am producing power from panels that are well in excess of my usage and I want to benefit from that with a better rate than the deemed export rate which assumes only 50%.

However if I install storage batteries cab I still get SEG export?

 

 

That is right you can swap your FIT  deemed export for SEG

There is some information here for anyone reading this

https://energysavingtrust.org.uk/grants-and-loans/feed-in-tariff/

SEG and battery storage isn't clear cut as it has been left up to suppliers, so you would need to check individual contracts

https://energysavingtrust.org.uk/advice/smart-export-guarantee/

Octopus currently process the vast majority of SEG applications, so it would probably be worth asking them if they can offer what you are after.

Have a look at the Outgoing Octopus Product (different from their standard SEG offer) . This does allow batteries, you can charge the batteries from the grid, and you can give up your deemed export FIT for this. There are some time limitations.

From the Octopus website. 

Under FiT guidelines, you get paid for being a generator, and paid for whatever you export.

You won’t be able to receive FiT export payments whilst also being on the Outgoing Octopus tariff. However, you will still be able to receive your generation payments. When you sign up to the Outgoing Octopus, you will be required to opt out of your deemed export payments from your existing FiT supplier (but there’s no requirement to switch your FiT contract to Octopus.)

For new installations (that is, after the FiT closure date of 1/4/2019) we’ll still require a copy of your Microgeneration Certificate Scheme (MSC) certification in order to get you onto the tariff.

BPLightlog
Super User
Super User
February 16, 2023

Hi @jaybell I have a FIT scheme not SEG so I’m not sure of the full SEG rules. I do know that under FIT you are not allowed to export from a battery storage system and generally the assumed 50% export is more than actual - yours may of course be quite different. 
Presumably you have a generation meter, separate to the smart meter but then you are looking to use the smart meter to measure export?

Bring me Sunshine ~ E&E {Solar PV, Battery Storage, Hybrid EV, ASHP and Home Assistant automation}