Do OVO offer 3 phase smart meters?

 

3 phase (aka polyphase) installations in domestic properties are few and far between, so it's a minority of meter engineers across the country that have the skills required to complete these installations. There are also some technical challenges in making sure your job is allocated to an engineer with these skills but we are just as keen as you are to have Smart available for these sites ASAP, so if you would like to take part in this beta stage release, please consider the steps below:


If you have a single rate 3 phase meter (i.e. not Economy 7 / 2-rate etc.) we would encourage you to book a smart meter appointment as normal online or over the phone on 0330 303 5063. 


This will then go through to a specialist team who will validate that it is single rate job and that an 3 phase engineer is available in your region. If this is the case, they will re-book your appointment with the right engineer. (So please bear in mind your appointment date/time will likely change, but we'll try to keep it the same where possible.)


Unfortunately, if you have a 2-rate meter or are not in an area covered by our current crop of 3 phase skilled engineers, you will need to continue with your heritage meter. We know this will be frustrating, so we are sorry about that, we are working to expand our coverage and by you flagging your interest to us, you are helping us shape where and when that coverage develops. - thank you!

 

OVO member but not got a smart meter yet? - Book today!

 

Interested but not yet an OVO member? - Check out our plans!

 

156 replies

Transparent
Rank 20
Rank 20
April 7, 2019

Updated on 26/06/24 by Emmanuelle_OVO:

 

Do OVO offer 3 phase smart meters?

 

3 phase (aka polyphase) installations in domestic properties are few and far between, so it's a minority of meter engineers across the country that have the skills required to complete these installations. There are also some technical challenges in making sure your job is allocated to an engineer with these skills but we are just as keen as you are to have Smart available for these sites ASAP, so if you would like to take part in this beta stage release, please consider the steps below:


If you have a single rate 3 phase meter (i.e. not Economy 7 / 2-rate etc.) we would encourage you to book a smart meter appointment as normal online or over the phone on 0330 303 5063. 


This will then go through to a specialist team who will validate that it is single rate job and that an 3 phase engineer is available in your region. If this is the case, they will re-book your appointment with the right engineer. (So please bear in mind your appointment date/time will likely change, but we'll try to keep it the same where possible.)


Unfortunately, if you have a 2-rate meter or are not in an area covered by our current crop of 3 phase skilled engineers, you will need to continue with your heritage meter. We know this will be frustrating, so we are sorry about that, we are working to expand our coverage and by you flagging your interest to us, you are helping us shape where and when that coverage develops. - thank you!

 

OVO member but not got a smart meter yet? - Book today!

 

Interested but not yet an OVO member? - Check out our plans!

 

Save energy... recycle electrons!
Newcomer
October 20, 2019

I read the topic and responses with disappointment. OVO cannot fit 3-phase smart meters. The work-around is either downgrading to a single-phase supply or having 3 separate single-phase meters for each of the 3 phases!

In another property my supply is from another provider. I have a single meter (Alster A1140); it is a smart meter, its has economy 7 on at all phases.

Why cannot OVO provide one like this?

Tim_OVO
OVO Staff
OVO Forum Legend
October 24, 2019

Tis a good question, @MARGARETMAVIS - have a look at Transparent’s ‘best answer’ at the top. It’s not something we can change directly at the moment. 

 

To discus supply downgrade options and costs, give us a call: 0330 303 5063

Carbon neutral - we need a community to get there! My green tech: Aclara SGM 1411-B smart meter, Chameleon IHD6
Newcomer
November 5, 2020

do ovo offer a 3 phase supply with economy 7 (or similar) - and how long would it take to get a meter installed on a new supply

Transparent
Rank 20
Rank 20
November 5, 2020

Hi @boulterc99  and welcome to the Forum.

At this time OVO don’t yet have 3-phase Smart Meters approved for installation, so the answer to your question depends on whether you are happy with a “traditional” meter.

There’s a basic Tutorial on single/three phase supplies here, which doesn’t go into great technical depth.

And there are a few other discussion Topics which raise issues of 3-phase connection in greater detail. This one about the requirement for vector-sum metering if you wish to export back to the grid is worthwhile reading.

Save energy... recycle electrons!
Newcomer
November 5, 2020

Thanks @Transparent smart meter is a nice to have, more interested in Economy 7 with 3 phase so i can recharge my batteries at night.

Transparent
Rank 20
Rank 20
November 5, 2020

OK, so if you’re happy with a traditional meter at the moment, then the next question is whether OVO have yet obtained a licence from Ofgem to install meters on new supplies.

This process is somewhat different to changing a meter on an existing supply and requires liaison with the regional Distribution Network Operator (DNO) and ECOES, the national meter database.

New feed meter installations used to be the province of the Big-6 Energy Suppliers, although a number of private companies are also now approved to do this work on new estates. OVO became the 3rd largest Supplier a year ago, but I haven’t yet seen any announcement that they are authorised to do new installs.

Let’s ask the Moderator, @Tim_OVO, if he can find this out for you.

Save energy... recycle electrons!
Newcomer
November 5, 2020

we have a single phase (via Octopus Energy) temporary supply for our new build but getting them to commit a date for installing a 3 phase meter is impossible hence looking elsewhere

 

Transparent
Rank 20
Rank 20
November 5, 2020

That existing meter on the temporary supply might make all the difference! :slight_smile:

I have experience as a self-builder, so I appreciate what you’re up against.

  • Was the cable for that temporary supply run onto your property by the DNO?
  • Does it connect to you from an overhead supply (on a pole) or an underground supply?
  • Do you now have an approved meter-box within the outside wall of your new-build?
  • Does your new meter position have any (non-energised) cable running to it? (in a duct?)

And please complete your Forum Profile page. It gives us basic background details such as your geographical area. Thanks.

Save energy... recycle electrons!
Newcomer
November 5, 2020

Hi Transparent

in line answers

  • Was the cable for that temporary supply run onto your property by the DNO?
    • Yes SSEN put in a new Wavecon cable for me as part of the temporary supply
  • Does it connect to you from an overhead supply (on a pole) or an underground supply?
    • Underground supply
  • Do you now have an approved meter-box within the outside wall of your new-build?
    • termination of 3 phase being put in the garage plant room (already inspected location by SSEN)
  • Does your new meter position have any (non-energised) cable running to it? (in a duct?)
    • House cables running to the garage plant room to fuse boxes are in ground in ducts
    • The new 3 phase cable trench is dug for SSEN to connect up to the Wavecon put in as part of the temp supply and this will be in a duct too
    •