Skip to main content
Rank 1
June 24, 2025
Solved

Smart meter installation Earth wire problem - Will my installation go ahead?

  • June 24, 2025
  • 4 replies
  • 200 views

I am trying to get a smart meter installed but was told when they attended that there was a problem with the earth wire so couldn't install it. 

I rent so reported what was said to my landlord & they sent an electrician but I was told that uk power network would contact me but I never heard from them. 

I really have no idea and don't want to book another insulation just for the same thing to happen again. 

Anyone able to tell me what the problem it please. 

.

Best answer by Lukepeniket_OVO

Updated on 04/07/25 by Abby_OVO

 

Hello!! 

I can see this appointment is booked in for today? a B07 issue was raised over a year ago so I assume UKPN have been out to fix the issue? although I cant see a decent photo from the previous job.

Looking at it I don’t see a reason why the job cant go ahead…

 

morning!! 

Yes it looks like a nice new L&G 5T was fitted =]

 

4 replies

Blastoise186
Super User
Super User
June 24, 2025

Hi ​@Webby77 ,

This sounds like a good one for ​@Lukepeniket_OVO as it’s engineer stuff. I’ll ask him to swing by so he can take a look at this.

Please bear with us - Luke may need a couple of days before he can stop by.

Securing energy by zapping security bugs... For that is The Blastoise Way! Remember, I'm just like you - AI Powered Evil Geniuses aren't Staff!
OVO Engineer
June 27, 2025

Updated on 04/07/25 by Abby_OVO

 

Hello!! 

I can see this appointment is booked in for today? a B07 issue was raised over a year ago so I assume UKPN have been out to fix the issue? although I cant see a decent photo from the previous job.

Looking at it I don’t see a reason why the job cant go ahead…

 

morning!! 

Yes it looks like a nice new L&G 5T was fitted =]

 

OVO Operations Excellence Manager and Former Field Operations Team Leader
Chris_OVO
Community Manager
Community Manager
June 30, 2025

Morning ​@Webby77

 

Did you manage to get the work carried out in the appointment ​@Lukepeniket_OVO has mentioned above? 

 

Please keep us updated and if you’ve got any further questions.

Renewable energy jokes never get old.
OVO Engineer
June 30, 2025

morning!! 

Yes it looks like a nice new L&G 5T was fitted =]