Hello.  I want to install a 5KW battery and have contracted with supplier. Iam now tokld ther is an up to 3 month delay in the approval of G99  applications even for fast track and approved systems.

comments please!

Best answer by Chris_OVO

Updated on 07/10/24 by Shads_OVO

I would agree with @BPLightlog after reading similar comments from members. It seems to be quite the lengthy process. We have heard that once accepted the form is normally emailed across fairly quickly

Have a read at the the article below which might help you when you apply for your SEG account when you get the process completed @jaybell 

Applied for OVO's smart export guarantee (SEG) - how long till it's set up?

 

Keep us updated on your progress! 

2 replies

BPLightlog
Plan Zero Hero
Forum|alt.badge.img+5
  • Plan Zero Hero
  • April 2, 2024

Having been through a similar process end of last year I’m not surprised. I think it depends on your DNO as there are more battery additions now also being made with the vat situation now in favour


Chris_OVO
Community Manager
Forum|alt.badge.img
  • Community Manager
  • Answer
  • April 3, 2024

Updated on 07/10/24 by Shads_OVO

I would agree with @BPLightlog after reading similar comments from members. It seems to be quite the lengthy process. We have heard that once accepted the form is normally emailed across fairly quickly

Have a read at the the article below which might help you when you apply for your SEG account when you get the process completed @jaybell 

Applied for OVO's smart export guarantee (SEG) - how long till it's set up?

 

Keep us updated on your progress!