Commercial to domestic on CT meter

  • February 17, 2024
  • 11 replies
  • 1074 views

Hi there. This subject has been covered before but slightly ambiguous outcomes. 
 

I have had to install a new 3-phase supply at a domestic property, which was (over) rated by our electricians as needing a 3-phase 315A supply. The size of supply was based around having 3 electric car chargers and large heat pumps for the house and some large outbuildings. 
 

I couldn’t find any supplier who would provide a domestic contract on a CT meter, so have got a business contract with Eon until November 24. This contract has painful capacity fees and standing charges and isn’t very competitive on KWh rates either. 
 

I would like to revert to a domestic contract in November this year, so would love to clarify the following :

 

Will Ovo take on this account and revert to a domestic contract with existing CT meter?

 

Will I be able to export any excess energy generated by solar panels?

If my existing meter is not supported, would Ovo install a suitable CT meter to allow the contract to switch over?

 

I’d be hugely grateful for any advice, as it seems I’ve crept into quite a complicated situation. 
 

Thanks a lot

Best answer by Emmanuelle_OVO

Updated on 11/07/25 by Chris_OVO:

 

I asked one of our metering experts about your situation, they advised the following:

 

It's a slightly rare installation for domestic, but not that uncommon. We have several hundred domestic CT supplies. You’ll need an AMR meter installed, you won’t be able to have smart though, there isn't a smart CT solution.

 

As far as supporting it, our management of AMR isn't the best, but we can do it. If you want export too, you’ll need to get a Supplier to agree to purchase the energy, we don't anything to deal with this for AMR due to the small volumes. Or a way to get the reads.

 

I can see why you’ve had issues but shouldn’t be on a business structure, you are domestic so, under VAT and HMRC rules, should be on a domestic structure. We don't support new connections of AMR installs, we hardly support new connections on non CT/3 phase, but the type of meter should not affect you being supplied by any domestic supplier. You just can't have Smart, but must have AMR. 

11 replies

Smithy27Author
Rank 2
June 21, 2024

Thanks for that, very useful 

 

Smithy