DNO and G99 delays- I want a 5KW battery


Forum|alt.badge.img
  • Carbon Cutter*****
  • 30 replies

Hello.  I want to install a 5KW battery and have contracted with supplier. Iam now tokld ther is an up to 3 month delay in the approval of G99  applications even for fast track and approved systems.

comments please!

Best answer by Chris_OVO

Updated on 07/10/24 by Shads_OVO

I would agree with @BPLightlog after reading similar comments from members. It seems to be quite the lengthy process. We have heard that once accepted the form is normally emailed across fairly quickly

Have a read at the the article below which might help you when you apply for your SEG account when you get the process completed @jaybell 

Applied for OVO's smart export guarantee (SEG) - how long till it's set up?

 

Keep us updated on your progress! 

View original

2 replies

BPLightlog
Plan Zero Hero
Forum|alt.badge.img+5
  • Plan Zero Hero
  • 2733 replies
  • April 2, 2024

Having been through a similar process end of last year I’m not surprised. I think it depends on your DNO as there are more battery additions now also being made with the vat situation now in favour


Chris_OVO
Community Moderator
Forum|alt.badge.img
  • Community Moderator
  • 735 replies
  • Answer
  • April 3, 2024

Updated on 07/10/24 by Shads_OVO

I would agree with @BPLightlog after reading similar comments from members. It seems to be quite the lengthy process. We have heard that once accepted the form is normally emailed across fairly quickly

Have a read at the the article below which might help you when you apply for your SEG account when you get the process completed @jaybell 

Applied for OVO's smart export guarantee (SEG) - how long till it's set up?

 

Keep us updated on your progress! 


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings