What is the procedure for moving the security tags in the meter box outside?
Best answer by Transparent
Updated on 28/11/24 by Emmanuelle_OVO: In this scenario your first port of call would be to arrange with your energy supplier to have an isolator switch installed to allow for the work to your fuse box to be carried out safely by an electrician without it affecting the metering equipment.
If you can’t have an isolator fitted for a reason such as space restrictions then the supplier should be able to ‘de-energise’ the supply in the morning and ‘re-energise’ it in the afternoon.
If the supplier doesn't offer this service another Safe Isolation Provider (SIP) or Distribution Network Operator (DNO) should be able to support.