The meter EDMF GS60-B is locked on this message “Performing Key Establishment”??
Nobody seems to know what this means??
Any help will be most appreciated.
Henry.
The meter EDMF GS60-B is locked on this message “Performing Key Establishment”??
Nobody seems to know what this means??
Any help will be most appreciated.
Henry.
Howdy
Sounds like it’s not commissioned properly. Could you run it through this tool and tell me what errors or warnings you get?
Thanks!
It is not my meter but it would appear the engineer left without finishing his job!
You seem to be right Blastoise186
Thank you!!!
‘Commissioning’ a smart meter allows the meter to link up to the network and begin sending the readings to us automatically. The engineer should commission the smart meters during your installation but occasionally this might not be possible, so a follow up visit may be required.
You can check whether your Secure S1 Smart meter is commissioned by following the steps below:
On an Aclara S2 meter, check the meter is commissioned by checking the electricity smart meter communications hub (at the top of the meter). If the HAN light is not flashing, this suggests that it hasn’t been commissioned. Further to this, on the screen itself, a commissioned meter would have a signal bar and "HAN" written on it to indicate connection.
If you notice your meter is not sending us readings or may not have been commissioned, complete the smart meter health check form online and the results will go straight to the right team. You can find out more about the smart meter health checks in these helpful guides:
Second generation (S2) Aclara smart meter health check (SMHC)
First generation (S1) Secure smart meter health check (SMHC)
No account yet? Create an account